Unscheduling production orders


<< Prev   Next >>

You can clear a schedule that was generated for a production order's operations. This is called unscheduling.

To unschedule a production order:

  1. Go to Production.
  2. Under Production, click Production orders.
  3. Open a scheduled production order.
  4. Click Action > Unschedule.
  5. Click Post and close.

This functionality is identical to the unscheduling tool available in the Production planning and control workplace. To learn more, see Unscheduling operations for production orders.