Scheduling production orders
You can schedule operations for a production order to be performed at a specific date and time, depending on the production order's due date, availability of work centers, and other factors.
To schedule a production order:
- Go to Production.
- Under Production, click Production orders.
- Open a production order that already has work-in-progress documents generated for it.
- Click Action > Schedule.
- In the Scheduling settings window, specify the scheduling settings and click Continue.
- Click Post and close.
This functionality is identical to the scheduling tool available in the Production planning and control workplace. To learn more, see Scheduling operations for production orders.